Client
City of Roseville
Project Location
Placer County, California, USA
Summary of Services
Planning, design, and construction management
Project Scope
In 2000, HSe prepared a recycled water feasibility study that recommended a strategy for distributing recycled water to customers throughout Roseville, California. HSe has subsequently provided design and construction management for the first implementation phases of the recommended system, providing recycled water for seven schools, five parks, a golf course, median strips, and greenbelts.
Recycled water facilities have included one 1.5 MG (5.6 ML) and two 1.0 MG (3.8 ML) above ground steel tanks, one 1,900 gpm (10 ML/d) and one 7,200 gpm (40 ML/d) pump station, and over 25,000 LF (7,600 m) of pipelines.